KONTAN.CO.ID - JAKARTA. State-Owned Enterprises Minister Rini Soemarno has said the construction of the Jakarta-Bandung high-speed railway project will fail to meet its completion target in 2019 due to problems in land acquisition. She said in Jakarta on Monday as of now, the land acquisition only reached 54 percent of the 140-kilometer total length of the project, or 55 km. She added the constructor had prepared the construction on 22 km of acquired land and conducted land clearance on the remaining 33 km.
Jakarta-Bandung railway project won’t meet target: Minister
KONTAN.CO.ID - JAKARTA. State-Owned Enterprises Minister Rini Soemarno has said the construction of the Jakarta-Bandung high-speed railway project will fail to meet its completion target in 2019 due to problems in land acquisition. She said in Jakarta on Monday as of now, the land acquisition only reached 54 percent of the 140-kilometer total length of the project, or 55 km. She added the constructor had prepared the construction on 22 km of acquired land and conducted land clearance on the remaining 33 km.